June’s construction update

11 June 2020

At The Orchards, we remain committed to your retirement future, today more so than ever. We want to ensure your retirement plans remain on track. That means construction of our apartments and community spaces is continuing at our safe, hygienic worksite, with plenty of activity to report, including:

  • Plastering of The Residents Club area, plus installation of ceilings and external façade glass
  • Preparation of swimming pool, with tiling to commence soon
  • Installation of kitchen floor on upper ground floor, joinery and painting underway
  • Tiling, painting and installation of kitchen cabinets and bedroom robes underway in apartments levels 1–3
  • Completion of external façade cladding and curtain walls
  • Balustrading of external balconies continuing
  • External landscaping and planting is continuing.