There have been some major milestones reached lately. The beautiful villas at The Orchards are right on track for construction to begin in September!

  • Kane Constructions completed the Stage 3 Early Works in June 2021 – works included the new inground services infrastructure works and civil works
  • 25% pre sales were achieved months ahead of targeted date
  • Tendering for the Stage 3 Early Works Balance (Orchards Green) was completed in late May 2021 and a contractor was appointed in early June 2021
  • Submission to council for town planning secondary consent occurred in May 2021 and on track to be approved prior to appointment of a Main Works Builder
  • Stage 3 Main Works tendering is currently ongoing and Baptcare are on track to appoint a builder in late July 2021
  • Stage 3 Main Works is currently on track to begin construction in September 2021